Hjalleseskolen
Subcontract for Carsten Knudsen A/S in connection with roof renovation
Belvent project no.: 2023-059
The project scope included:
Delivery and installation of a new SystemAir Geniox 10, as well as modifications to the existing three SystemAir Geniox ventilation units. Designed air volumes from 2,500 to 8,500 m³/h. Installed outdoors on the roof.
Dismantling of old ventilation ducts and insulation.
Delivery and installation of new ventilation ducts with outdoor technical insulation.
Disassembly and reinstallation of fire and smoke dampers
Project Managers:
Martin Andersen
Head of project